Recently, the Technology and Construction Court decided the case of Belong (Construction) Limited (Belong) v Seddon Construction Limited (Seddon) [2026] EWHC 1275 (TCC) which determined that liabilities contained in a Pre-Construction Services Agreement (PCSA) (for pre-existing breaches) could survive even though the parties had subsequently entered into a JCT main contract. The terms and liabilities were not extinguished after the PCSA had been “subsumed into and subject to” a main JCT contract.
In May 2020, Belong had instructed Seddon (Defendant) to carry out works on a care home development pursuant to a PSCA. The PCSA incorporated Proposed Contract Documents (PCD) which included the draft main JCT Standard Building Contract. As part of the PCSA, Seddon was instructed to inspect, and carry out opening-up and testing of air sealing works (ASW). This had formerly been carried out by a previous contractor.
In December 2020, the parties entered into the JCT Contract. Importantly, the final executed JCT contract did not include the requirements for the ASW testing, as it was included in the PCDs. As a result, Seddon was instructed by the Contract Administrator (CA) to carry out the ASW. Seddon complied with the instruction, which resulted in a delay to its works. Seddon subsequently requested an extension of time (EOT) from the CA. The CA rejected the EOT. The CA maintained that the ASW were always required and any delay was simply a result of Seddon’s earlier breach of the PCSA and failure to carry out the ASW.
Belong focussed on the specific wording in the PCSA, specifically that the words “obligations” and “liabilities” were intentional. Belong argued that the liabilities continued into the JCT Contract for pre-existing breaches. To the contrary, Seddon argued that any PCSA obligations were “subsumed into and subject to” the JCT Contract and as such were replaced. It further argued that clauses 2.28.6.5 and 4.20.3 of the JCT Contract which prevented Seddon from claiming relief for events which arose from its own “error, omission, negligence or default” were limited to the JCT Contract.
The dispute led to an adjudication referred by Seddon. The adjudicator decided in favour of Seddon. This led Belong to bring about a Part 8 Claim, challenging the decision by the adjudicator and for final determination of the dispute.
The Court paid close attention to the wording of the contracts:
The Court ruled in Belong’s favour. Based on Seddon’s failure to comply with the requirements to inspect, and carry out opening-up and testing of the ASW, which were not extinguished by the entry to the JCT Contract, the Court upheld Belong’s contractual claim under the PCSA.